Willie O'Dea
question
15. Deputy Willie O'Dea asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation the action he is taking to overcome the key barriers to infrastructure delivery; and if he will make a statement on the matter. [27468/26]
Tony McCormack
(recorded as: Deputy Tony McCormack)
What action has the Minister taken to overcome the key barriers to infrastructure delivery?
Jack Chambers
(recorded as: Deputy Jack Chambers)
As Minister, I am responsible for setting the overall capital allocations across Departments and monitoring monthly expenditure at departmental level. The programme for Government set out clear prioritisation for the national development plan review to ensure that investment can be maximised in the coming five years for strategic infrastructure. Last year, my Department worked on the identification of barriers to infrastructure delivery. In December, it published the Accelerating Infrastructure Report and Action Plan, aimed at removing those barriers. This is critical to allow the Government to meet the increased supply of homes and support competitiveness. The plan sets out 30 targeted actions grouped under four pillars, each addressing a key area of reform. A key achievement in the first quarter has been the publication of the Critical Infrastructure Bill. Core regulatory foundations have also been put in place through the establishment of the infrastructure regulatory simplification unit; the issuance of cross-Government circulars on better regulation and reaction to legal precedent; and strengthened engagement with regulators and EU institutions to support legislative simplification. Progress has also been made on delivery and co-ordination with the completion of the national development plan review and sectoral investment plans; revised infrastructure guidelines approved and issued; enhanced National Development Finance Agency support arrangements for sponsors; and improved focus on priority projects. The removal of bottlenecks has been progressed through the joint utilities and transport clearing group. Capacity and productivity reforms within the construction sector have been advanced through publication of the workforce and skills plan and the restructuring of the construction sector group to drive procurement, innovation and digitalisation. Engagement to support leadership and public acceptance has intensified, and that work is ongoing. In quarter 2 of 2026, the focus will be on advancing priority legislation, progressing planning, regulatory and EU-related reforms, strengthening oversight of delivery risks and bottlenecks, embedding procurement and productivity initiatives and further improving co-ordination on utilities, land availability and public engagement to support timely delivery of critical infrastructure.
Tony McCormack
(recorded as: Deputy Tony McCormack)
I thank the Minister for the response. One of the key issues facing communities is the length of time it takes for major projects to move through the system. At present, pre-planning stages for major road projects can exceed one year, while electricity, water and wastewater infrastructure can take three or four years before delivery even begins. These delays are having a direct impact on housing and enterprise development and the ability of communities to grow and remain vibrant. Will the Minister outline the immediate actions being taken to reduce these timelines, as well as the new target timeframes he expects for roads, energy and water infrastructure?
Jack Chambers
(recorded as: Deputy Jack Chambers)
There are a few changes being made. I referenced the infrastructure guidelines earlier, and that is an important change. They will save significant time and they have already advanced. Separately, we are seeking to put in place a standardised template on business case development. We know a business case can take a short time with particular agencies and utilities but, in certain instances, it drifts into years. The wider public discussion often focuses on judicial reviews and reforms in that space - we need to advance that reform - but there is also a lot of time wasted at the early phase of a project around concept design. That is why the National Development Finance Agency is being stood up. It is broadening its remit to reduce the time at all elements of the project lifecycle. The Critical Infrastructure Bill will also help fast-track projects through the respective permitting, licensing and approval processes. The infrastructure task force is already bringing about reforms and changes to some of the regulatory functions that exist within regulators in respect of how they deliver infrastructure and how their processes need to be reformed to better enable infrastructure delivery.
Tony McCormack
(recorded as: Deputy Tony McCormack)
Communities want certainty that these delays are being tackled with urgency and that the providers of these utilities, especially in water, electricity and transport, are capable of doing the work that is needed. Will the Minister confirm when people can expect to see reduced timelines in practice, particularly for projects linked to housing and regional growth? How will the Department ensure that the acceleration of infrastructure delivery is felt across County Offaly, and indeed, across the whole island of Ireland?
Jack Chambers
(recorded as: Deputy Jack Chambers)
To build homes, we have to have transport, energy and water systems in place. That is why the work with utilities to build that enabling infrastructure is absolutely critical. There will be wider co-ordination with the housing activation office, which is working on this at a local level, for example, in Offaly. What are the opportunities to advance housing supply and growth at a local level? Where is there particular road or water infrastructure or a need from an energy perspective to advance housing supply? That work is happening with the housing activation office. What we are doing in my Department is with the utilities at a national level to remove the blockages, barriers and constraints to overall delivery, which they have. All of that will yield improved delivery, improved timelines and ultimately strengthen housing supply. We know from local authorities and developers that the infrastructure gap is something that constrains overall housing supply. All of this reform will help speed up the housing supply.
David Maxwell
(recorded as: An Cathaoirleach Gníomhach (Deputy David Maxwell))
We are moving to the last question.
Colm Burke
(recorded as: Deputy Colm Burke)
I indicated that I wanted to ask a supplementary question, which I am entitled to do.
David Maxwell
(recorded as: An Cathaoirleach Gníomhach (Deputy David Maxwell))
There are no supplementary questions. There is only six and a half minutes per question and there are no supplementary questions. That rule was made about three weeks ago. It was communicated to all TDs. Supplementary questions are out unless the TD asking the question gives time to the other TD. We move now to the last question, and we only have two minutes. Deputy Burke can ask his question, but I can only allow him back in once.